Wisconsin Preliminary Notice Requirements
Wisconsin requires you to send a "Preliminary Notice" to protect your mechanics lien rights. Here's everything you need to know — who to send it to, when to send it, and how to deliver it.
Yes
Must send to preserve lien rights
60 days
From first furnishing
No
Send on time
Preliminary
Understanding Preliminary Notices in Wisconsin
Wisconsin uses a preliminary notice system. Here's what that means in plain English: when you start working on a construction project (or deliver your first batch of materials), you need to send a document called the “Preliminary Notice” to certain people within 60 days.
Imagine you're an electrician hired to wire a new office building in Wisconsin. Your first day on the job site is March 1st. Under Wisconsin law, you need to send the Preliminary Notice by 60 days later. This notice goes to the property owner. Send it on time to keep your lien rights active. This is the single most important compliance step on any Wisconsin project.
Who Needs to Send a Preliminary Notice in Wisconsin?
This applies to nearly everyone who works on a construction project and wants to protect their payment rights. That includes general contractors, subcontractors (electricians, plumbers, roofers, etc.), material suppliers (lumber, concrete, fixtures), equipment rental companies, laborers, architects and engineers, and surveyors. The specific rules — like who you need to notify and your deadline — depend on your role. Check the table below to see exactly what applies to you.
Why Preliminary Notices Matter
The Preliminary Notice is what keeps your lien rights active in Wisconsin. It's standard paperwork — sending it on time protects your payment on every project.
Who Must Receive the Preliminary Notice?
Who you need to notify depends on your role on the project. Here's a simple breakdown:
| If You Are A... | You Must Notify... |
|---|---|
| General Contractor | Property Owner |
| Subcontractor | Property Owner |
| Material Supplier | Property Owner |
| Laborer | Property Owner |
| Equipment Rental Company | Property Owner |
| Architect / Engineer / Surveyor | Property Owner |
How to Deliver the Notice in Wisconsin
Use one of the approved delivery methods below to make sure your notice is valid. Wisconsin accepts these methods:
Certified Mail — You send via USPS and get a green receipt card proving the notice was delivered. This is the gold standard because it creates clear proof of delivery.
Personal Delivery — You (or someone you designate) hand-deliver the notice directly to the recipient. Make sure to get a signed acknowledgment as proof.
Statutory Notice Language
Wisconsin law requires your Preliminary Notice to include specific warning language. This isn't language you write yourself — it's exact wording specified by WI Stat. §§ 779.01 et seq.. Using the wrong language (or leaving it out) can invalidate your notice. LienGrid automatically includes the correct statutory language for Wisconsin.
Owner Warning Language (excerpt from WI Stat. §§ 779.01 et seq.)
NOTICE: AS A MATTER OF RIGHT, THE CONTRACTOR RETAINS A LIEN ON YOUR PROPERTY OR A LIEN ON THE FUNDS YOU ARE OBLIGATED TO PAY THE CONTRACTOR. IF ANY PERSON OR COMPANY THAT PERFORMS WORK ON YOUR PROPERTY OR PROVIDES MATERIAL FOR THAT PROJECT FAILS TO RECEIVE PAYMENT, A LIEN MAY BE PLACED ON YOUR HOME.
Official Wisconsin Resources
These are official state government websites where you can look up statutes, verify contractor licenses, and search business registrations.
Preliminary Notice Requirements by County in Wisconsin
Select your county for specific guidance on sending preliminary notices in your area.
72 counties found
Wisconsin Preliminary Notice FAQ
Common questions about preliminary notices in Wisconsin, answered so anyone can understand.
Preliminary Notice Rules in Neighboring States
This information is for general guidance only and does not constitute legal advice. Wisconsin laws change frequently — always verify current requirements and consult a licensed attorney in the relevant jurisdiction before taking legal action. LienGrid makes every effort to keep this information accurate, but we cannot guarantee completeness or currency.